A meeting was held to analyze the latest progress of the Saqqez gold extraction plant construction project.

A meeting was held to analyze the latest progress of the Saqqez gold extraction plant construction project.


Aziz Mohammadi, providing explanations about the actions taken, said: "With time management, we are trying to compensate for the delays by shortening the time for holding tenders.
" Miqdad Majdi, CEO of the Kurdistan Gold Mines Development Company, also stated that the weather limitations in the Kurdistan region would significantly reduce the effective timeframe for field operations. He added: "We hope that IRITEC, considering all aspects of the work, will fully utilize the contractual capacities and, by implementing new solutions within the framework of the agreement, will leverage its legal capacities to make up for the existing delays."

طلای کردستان
طلای کردستان

The Saqqez Gold Extraction Plant construction project, contracted to the International Engineering Company of Iran (IRITEC), is underway with an investment of over 1,250 billion tomans by TASICO. In other areas of the company's projects, over 300 billion tomans will be invested this year in exploration and mining extraction. The cumulative progress of the Kurdistan Gold Mines Development Company's projects in the mining sectors (including extraction and exploration) and the plant is approximately 14%. This company will create direct employment for 350 individuals in the region.